After putting a camera down the main line (AWA sewer pipe) we found a clay “T” junction. This can mean there is a lateral going to the property, but the chances are it will be just a “T” junction.
The road in Weston had to be closed, this will take 3 months, this will cost up to £600 in Lincolnshire but it can cost more in other areas.
The work was carried out on the 21st October 2015, it took 2 days.
Went down 1.9 metres, it was a junction only.